Northwest corner of hallway where it meets the southeast corner of walk in cooler. 

Northwest corner of hallway where it meets the southeast corner of walk in cooler. 

 Joe Sheehan installing 5/8ths OSB on north side of hallway. (Two ladder man)

Joe Sheehan installing 5/8ths OSB on north side of hallway. (Two ladder man)

 Core bond insulation being sprayed on the inside of the walk in cooler.

Core bond insulation being sprayed on the inside of the walk in cooler.

 12' ponderosa beetle kill stained pine for bar top. (1 of 2) 

12' ponderosa beetle kill stained pine for bar top. (1 of 2) 

 North side (production area) of hallway.  

North side (production area) of hallway.  

 Inside of hallway sheet rocked and looking west. 

Inside of hallway sheet rocked and looking west. 

 Inside of hallway looking east.  

Inside of hallway looking east.  

So that's what we've been up to the last 2 months! Things to finish up include tapeing and mudding the drywall, painting, plumbing, electric, concrete floor finishing, cooling condenser and evaporating unit, cooler doors, building the bar.. probably a thing or two more but getting closer!!